‘klia2 rectification work to start immediately’

By Khairie Hisyam

klia2-design-2Rectification work will commence immediately to tackle the cause of the delay in handing over klia2’s main terminal building to Malaysia Airports Holdings Berhad (MAHB), said joint venture partners UEM Construction Sdn Bhd (UEMC) and Bina Puri Sdn Bhd.

In a press statement late yesterday evening, the JV partners confirmed that they have yet to receive a Certificate of Completion and Compliance (CCC) for their klia2 work package due to an “unexpected issue” which arose during a follow-up inspection.

Accordingly UEMC–Bina Puri said they have discussed and are working with MAHB as well as the authorities, consultants and architects to address the issue and will begin repair works immediately.

“Public safety is the main priority, thus we will ensure proper rectification works are diligently carried out,” said both companies in a joint statement. “At the same time, UEMC–Bina Puri JV will work together with MAHB on the next course of action in regard to the issuance of the CCC and the commencement of Operational Readiness and Airport Transfer (ORAT).”

However, representatives of the JV partners declined to elaborate when contacted by KiniBiz regarding the nature of the issue.

KiniBiz reported yesterday that the issue is damage found in sewerage pipes underneath the main terminal building caused by soil settlement, which is not the first time soil condition has come to the fore as an alleged cause of delays.

KiniBiz understands that the affected sewerage pipe is about 100 metres long.

“It is possibly a design flaw,” said another source with knowledge of the matter on the damage to sewerage pipes, adding that the contractor responsible has proposed rectification measures to fix the issue.

“Nothing to do with workmanship … it’s an issue with the soil condition,” added the source who requested anonymity.

According to a source familiar with the matter, deputy transport minister Abdul Aziz Kaprawi chaired a “heated” meeting over the issue early yesterday. KiniBiz was informed that preliminary ORAT activities have also begun yesterday.

In December a report noted that there were cracks on the airport apron area indicating “an uneven surface and a poor drainage system”.

UEMC and Bina Puri’s work package, worth RM997 million, comprises the design, construction, commissioning and maintenance of the main terminal building of klia2, a satellite building, sky-bridge and piers.

A separate statement from MAHB said that the main terminal building also failed fire and safety checks by local authorities last month, with some 65% of the building not in compliance with fire and safety standards.

No new target date yet

Despite the handover delay, there has been no indication yet of a new opening date for klia which was set for May 2, 2014.

A source familiar with the matter said the May opening date is still possible if all parties work towards making it happen, although acknowledging that it is still a challenging task.

Should this latest glitch lead to an opening reschedule, it would mark the fifth delay for klia2 in less than three years.

Conceptualised in 2007, the original completion target for the new airport was September 2011, but this was pushed back to April 2012 to accommodate design changes brought about by Air Asia’s changing business model which requires space for transfer and transit passengers as well as baggage transfer handling facilities.

airasia-logo-klia2Air Asia is set to be the main user of klia2, with an estimated 80―90% of the initial traffic estimated by Maybank KE to come from the low cost carrier and airport industry officials has noted that Air Asia, despite being a vocal critic in the klia2 saga, has to shoulder part of the blame in the repeated delays.

The 2012 date was later rescheduled to April 2013 following a change in specifications which included adding aerobridges, upgrading the baggage handling system to be automated and  lengthening the runway from the original 2.5km to 3.96km. Accordingly the construction cost was officially raised from RM2 billion to around RM3.6―3.9 billion.

However, the April 2013 target was then pushed further to June 28, 2013 to coincide with the date of Kuala Lumpur International Airport (KLIA) began operations in 1998.

Missing the June 2013 deadline has led to MAHB claiming RM199,445.40 in liquidated ascertained damages (LAD) daily since June 16, 2013 from the UEMC―Bina Puri partnership.Two days after the 13th general election on May 5, 2013, however, the launch date was rescheduled again to May 2014.

KiniBiz previously examined the klia2 issue in a four-part series here.